Dam Construction Requires Financing in HondurasThe construction project for the Jicatuyo and Los Llanitos dams still needs $150 million in funding.Monday, August 15, 2011 The project has already raised $100 million from the Brazilian National Bank, $200 million from Banco Centroamericano de Inversión, $20 million of the Brazillian company Odebrecht (who will carry out the works) and $100 million from Empresa Nacional de Energía Eléctrica, ENEE. Source: laprensahn.com Honduras: Hydro Power Plants Move ForwardMarch 2010 Brazilian businessmen are holding meetings with government authorities in order to speed up the construction of hydro power plants Jicatuyo and Los Llanitos. $600 million for hydroelectric plant in HondurasJanuary 2009 The Odebrecht company will be in charge of constructing the Los Llanitos and the Jicatuyo hydroelectric dams in the Santa Barbara department. Honduras: Approves Construction of HydroelectricJanuary 2011 Congress passed a law permitting construction of hydroelectric plant Patuca I, II and III and Los Llanitos and Jicatuyo. |
![]()
|