El Salvador: “Chaparral” Dam 25% ReadyHydro power plant “El Chaparral”, located over Torola river, to the north of San Miguel, is 25% ready.Friday, February 26, 2010 ![]() It is progressing according to schedule, and should be ready by January 2013. Source: laprensagrafica.com El Chaparral Hydro Power Plant in 2013August 2009 The president of CEL announced that the project is going according to schedule, and will be ready in January 2013. Construction Halted at Chaparral Hydro Power ProjectJune 2010 In El Salvador, tropical storm Agatha has caused floods which forced the contractor to temporary suspend the construction of this hydroelectric power plant. Two Additional Years to Redesign El ChaparralJune 2011 The Salvadoran regulator has granted a period of two years for the submission of a redesign of the project, currently on hold. Chaparral Hydro Power Plant is 22% ReadyMay 2010 17 months after starting construction, hydroelectric power plant “El Chaparral”, located in San Miguel, is 22% ready. |
![]()
|